10 Material suppliers

Specified by grade. Tested before it is buried.

We specify materials by standard and grade rather than by brand, so you can compare quotes honestly. Where you want a particular brand, we will price it and say plainly whether it is worth the difference.

SHEET 10 — MATERIALS
Material Specification Source Testing
Cement OPC 53 grade to NS 572, in 50 kg bags Two valley plants, direct despatch Mill certificate per lot
Reinforcement Fe500D TMT, 8–25 mm Authorised dealer, Balkumari Tensile test per 20 t
Bricks Machine-made, first class, min. 35 kg/cm² Kilns at Bhaktapur and Lubhu Crushing test per 50,000
Facing brick Dachi apa for restoration work Traditional kiln, Thimi Visual and sample panel
Coarse aggregate 20 mm and 12 mm crushed stone Crushers along the Bagmati corridor Sieve and impact test
Sand Coarse river sand, silt below 5% Approved quarries, Nuwakot Silt test on every delivery
Ready-mix concrete M20 to M30, design mix Batching plants at Chapagaun Slump + cubes at 7 and 28 days
Waterproofing Crystalline slurry and SBS membrane Authorised importer, Kathmandu 48-hour ponding test
Paints Acrylic exterior, washable interior emulsion Dealer, Kupondole Batch record retained
uPVC & aluminium Multi-chamber uPVC, powder-coated aluminium Fabricators, Balkumari Water and sample check

How material reaches your site

  • Call-off dates set six weeks ahead against the programme
  • Every delivery weighed or counted at the gate and entered in the site register
  • Cement stacked on a raised platform, maximum ten bags high, oldest used first
  • Rod stored off the ground and clear of standing water
  • Rejected material sent back the same day — it is never quietly used elsewhere

If you supply the material

Plenty of owners buy their own cement, rod and brick. That is fine, and we will run the job labour-only — with two conditions.

  • Material must meet the written specification; we test it the same way regardless of who bought it
  • Delivery must meet the call-off dates, or the programme moves and the extension is yours