An estimate is a document, not a phone call.
You will get an item-wise bill of quantities with rates traceable to the Lalitpur district rate for the current fiscal year. If a line is provisional, it says so on the page.
From enquiry to signed contract
| Stage | What happens | Time | Cost |
|---|---|---|---|
| 01 · Enquiry | Call or form. We ask for plot size, ward, and what you want to build. | Same day | Free |
| 02 · Site visit | Measurement, access check, setback and soil observation, neighbour constraints. | 3–5 days | Free in Lalitpur |
| 03 · Concept | Two plan options and a rough cost band, so you can decide before paying for drawings. | 7–10 days | NPR 15,000 |
| 04 · Working drawings | Architectural, structural, electrical and sanitary sets signed by licensed engineers. | 3–4 weeks | NPR 28–45 / sq ft |
| 05 · Detailed estimate | Item-wise BOQ, rate analysis, abstract of cost, and a cash-flow schedule. | 7 days | Free with drawings |
| 06 · Contract | Scope, rates, payment stages, programme and defect liability signed by both parties. | 3–5 days | — |
What is inside the estimate
- Item-wise BOQ following the Lalitpur district rate for FY 2082/83
- Rate analysis for every non-standard item, showing labour and material split
- Material specification by grade, not by brand, unless you ask for a brand
- Contingency of 5–8% shown as a separate line, never hidden in the rates
- Payment schedule tied to physical milestones, not to calendar dates
- Exclusions listed explicitly on the last page
What moves the number after signing
- Client-instructed variations — priced from the same rate schedule
- Ground conditions worse than the trial pit indicated
- Cement or rod price movement beyond ±8%, adjusted per the contract clause
- Municipal design conditions imposed after the permit review
- Extension of time granted for events outside our control
Payment stages — private house
10% on signing · 15% at plinth · 20% at first slab · 20% at top slab · 15% at plaster · 15% at finishing · 5% retained for 12 months of defect liability.