04 Permits & licences

The naksa pass, filed and followed up.

Building permission in Lalitpur Metropolitan City runs through your ward office and the urban development section. We prepare the file, submit it, attend the technical queries and book the inspections. You sign; we queue.

SHEET 04 — PERMITS & LICENCES

Documents we will need from you

  • Land ownership certificate (lalpurja), original and two copies
  • Blueprint and field book trace from the survey office
  • Citizenship certificate copies of all registered owners
  • Land revenue receipt for the current fiscal year
  • Consent letter where the plot is jointly owned
  • Photographs of the plot showing the access road

What we prepare and submit

  • Architectural drawing set signed by a registered architect
  • Structural drawings and design report to NBC 105:2020
  • Soil test report where the municipality asks for one
  • Ward recommendation application and follow-up
  • Permit application with the fee calculation sheet
  • Inspection bookings at plinth, superstructure and completion
Permit sequence
Step Office Outcome Working days
01 Ward office Recommendation letter for the plot 3–7
02 Metropolitan urban development section Drawing registration and file opening 2–4
03 Technical review Setback, ground coverage, height and code check 7–15
04 Fee counter Permit fee assessed and paid 1–2
05 Permit issue Construction permission — work may start 3–5
06 Plinth inspection DPC level verified against the approved drawing At plinth
07 Superstructure permission Clearance to build above plinth level 5–10
08 Completion certificate Final inspection and building completion record 10–21

Typical total from ward recommendation to permit is 21–45 working days for a private house. Plots in heritage-controlled areas, on sloping ground, or with disputed access take longer. Municipal fees are paid by the owner directly at the counter — we never handle permit cash.

Our own licences
Registrations
Contractor licence Class "B", building & civil
Issued by Dept. of Urban Development
Registration no. 4127/058/059
Renewed Shrawan 2082
Company registration Office of the Company Registrar
PAN 301674528
VAT Registered, monthly filing
Labour registration Lalitpur labour office

Our licence class limits the contract value we may hold at one time under public procurement. For private work there is no such ceiling, but we hold to the same limit voluntarily so that no single job can starve another of crew or cash.

Three of our engineers hold current registration with the Nepal Engineering Council. Structural design is always signed by the registered engineer who did it — we do not sign other people's calculations.