Jawalakhel, Lalitpur–02

Ashok retail & office block

Complete 21,400 sq ft 21 months Item rate with a certified monthly bill
SHEET 02 — MCC-206

Retail at ground and first floor, offices above, on a main-road plot with no side access and a footpath that had to stay open throughout. The largest job we have run inside the ring road.

The ground floor was handed to tenants three weeks ahead of the contract date, which mattered more to the client than anything else in the programme.

Job record
Job no. MCC-206
Type RCC framed commercial block, five storeys
Location Jawalakhel, Lalitpur–02
Area 21,400 sq ft
Client Ashok Tuladhar
Contract Item rate with a certified monthly bill
Structural engineer R. Shrestha, NEC 12408
Code basis NBC 105:2020 · fire and access review by the metropolitan office
Duration 21 months
Handover Poush 2081

Scope of works

  • Piled retaining to the boundary where excavation abutted the footpath
  • RCC frame with a 7.2 m grid to keep the retail floor clear
  • Passenger lift shaft and staircase core cast in slip stages
  • Glazed shopfront and aluminium curtain glazing above
  • Fire staircase, hydrant line and detection to the approved layout
  • Tenant fit-out coordination for four separate retail units

Key dates

Contract signed Chaitra 2079
Frame topped out Magh 2080
Ground floor released to tenants Mangsir 2081
Handed over Poush 2081
What was difficult
Every delivery arrived on a live main road. We took a night-delivery permit from the ward, unloaded between 21:00 and 05:00 for eleven months, and kept a flagman on the footpath in daylight hours. It cost about 4% of the labour budget and avoided every complaint we expected.
“We opened the ground floor to tenants three weeks before the contract date. In this city that is not normal.”
Ashok Tuladhar, owner — MCC-206 · Poush 2081