A modest two-storey house built on a labour-only contract, where the owner bought her own cement, reinforcement and bricks. We supervised, supplied the crew, plant and formwork, and tested every material exactly as we would have if we had bought it.
One brick delivery was rejected on arrival for under-burning. The owner queried it, we crushed three samples in front of her, and the load went back the same afternoon.
Job record
Job no.
MCC-203
Type
RCC framed house, two storeys
Location
Imadol, Lalitpur–17
Area
2,240 sq ft
Client
Sarita Maharjan
Contract
Labour only — owner supplied materials
Structural engineer
S. Ghimire, NEC 15721
Code basis
NBC 105:2020 · NBC 205
Duration
11 months
Handover
Mangsir 2081
Scope of works
- Layout, excavation, PCC and isolated footings
- Reinforcement fixing to the bar bending schedule, owner-supplied rod
- Formwork, casting and curing of the frame across two floors
- Brick masonry and two-coat plaster
- Terrace waterproofing and screed
- Supervision of the owner's own electrical and plumbing trades
Key dates
| Contract signed | Poush 2080 |
| Plinth inspection cleared | Falgun 2080 |
| Top slab cast — Asar rain | Asar 2081 |
| Handed over | Mangsir 2081 |
What was difficult
The top slab had to be cast in Asar with rain forecast. We tented the pour area, kept the mix drier at the plant, cast in one continuous session with a standby mixer, and covered it within twenty minutes of the final float. Cubes came back at 26.4 N/mm² at 28 days against a design of 20.
“They poured our slab in Asar with the rain coming down and still gave us cube results at 28 days. Nothing on the bill was a surprise.”