01.2 Commercial construction

Buildings that have to open on a date.

Commercial work is judged on the programme, not the drawing. Our commercial jobs run to a bar-chart programme with a weekly look-ahead, a named engineer, and a monthly bill certified by your consultant before we ask for payment.

SHEET 01.2 — COMMERCIAL

Sectors we have built for

  • Office and mixed retail blocks — Jawalakhel, Kupondole, Pulchowk
  • Warehouses and logistics sheds — Ekantakuna, Satdobato
  • Schools, hostels and training institutes
  • Clinics, diagnostic centres and pharmacy fit-outs
  • Restaurants, cafés and small hotel shells
  • Ward offices and community buildings under municipal tender

What comes with a commercial contract

  • Programme in bar-chart form, with the critical path marked
  • Named project engineer and a site supervisor on full-time posting
  • Monthly measured bill with abstract, measurement sheet and photographs
  • Performance bond of 5% and advance payment guarantee where required
  • Contractor's All Risk cover naming the client as co-insured
  • Two-week defect snag cycle before handover, then 12 months' liability
Typical durations
Building Scope Structure To handover
Retail block 4 storey, 18,000–24,000 sq ft, RCC frame 9 months 19–22 months
Warehouse Single volume, 8,000–15,000 sq ft, steel truss roof 5 months 8–10 months
School block 3 storey, 12 classrooms, NBC 205 compliant 7 months 13–15 months
Clinic fit-out Within an existing shell, 3,000–6,000 sq ft 4–6 months

Durations assume the permit is in hand and exclude the monsoon buffer (Asar to Bhadra) and the festival shutdown around Dashain and Tihar, which together account for about 34 working days a year.